It is now possible for a task with only a start date to repeat from that start date. The new behavior is as follows.
1) If the repeating task only has a due date: The due date will be used to determine when to reschedule the task. The start date will remain empty.
2) If the repeating task only has a start date: The start date will be used to determine when to reschedule the task. The due date will remain empty.
3) If the repeating task has both a due date and a start date: The due date will be used to determine when to reschedule the task. The start date will be moved forward by the same amount that the due date is moved.
Previous to this update, scenario #2 wasn't possible.
|