ForumsTips & TricksTasks completed list in completed date order.
Tasks completed list in completed date order.
Author |
Message |
cameronzayec
|
Hello,
At the end of each day, I would really like to see the tasks I have completed for the day.
I am aware of the 'History', however they are ordered in task start date order, which is not very helpful.
I would like to keep all of my completed tasks, but I think my only option is to delete my history at the end of each day...
Can anyone provide some advice?
Thanks.
|
PeterW
|
Simplest way would be to create a search and save it. It is then available as a tab and can be used every day.
Criteria would simply be:
Checked off = yes
Completed date = today
You can also see completed tasks in the Main view - Recently Completed tab although this shows more than the current date.
|
You cannot reply yet
U Back to topic home
R Post a reply
To participate in these forums, you must be signed in.